Recently I loaded up some team members with a large amount of Templated Tasks. There is not really enough time to back fill details in the Tasks from the PBI nor do I think someone needs to do this as that Task is linked to the PBI.

However, some team members use the "My Tasks" query. Due to my loading of template tasks their query results in a bunch of tasks that have little detail unless they dive into the links open the PBI, and then maybe dive into other tasks and open them. Quite tedious.

To correct this issue temporarily I have provided a query using the backlog board with Tasks being visible and then added a clause to the Linked Items (the tree view) to only show items assigned to them. This works.

However, the query also returns all of the PBIs as I have not adjusted the top part of the query.

Is there a way to not show PBIs that the user does not have a Task for?
What clauses would I use?

Again, I want to show the Treeview of Parent PBI and its tasks so the details of the PBI do not need to be added to the task. As an example, we may have a task to "Update User Guide" and it is dependent on what happens in other Child tasks of the PBI.
Posted
Updated 20-Aug-14 6:32am
v2

This content, along with any associated source code and files, is licensed under The Code Project Open License (CPOL)



CodeProject, 20 Bay Street, 11th Floor Toronto, Ontario, Canada M5J 2N8 +1 (416) 849-8900